Update on Phase 2

The section around Dark Deer has now been dug out and prepared for surfacing work. Due to presence of livestock this can’t be completed until the internal fence is installed. Work on external deer fence is now underway. Work is … Continue reading

Posted in AKW News

Timber Operations Sep-Nov

FLS has advised of timber operations impinging on the AKW from now till November. Tree felling is taking place in the yellow area on the map below. The AKW will remain open but you are asked to follow the safety … Continue reading

Posted in AKW News

Phase 2 Work Underway

After some unavoidable delays work has commenced on Phase 2. Initially our contractor Hitrak Ltd will deal with a very ‘wet’ section requiring a deep base. This is being installed using recyled stone from old walls within the croft.